Orofino Bridge Construction Update

Construction on the new Orofino Creek Bridge is continuing as scheduled. Pile driving will start on Tuesday, July 7. This generates a lot of noise. A member of the construction team will visit with nearby residences, specifically affected by the pile driving activities. Ear plugs will be available to residents, if needed. 

During construction traffic will have to go around Harmony Heights Loop via the Deer Creek Road side.

The project is expected to last approximately 90-days. Work is scheduled Monday-Friday during daytime hours. Motorists are encouraged to slow down and pay attention when traveling in this area. 

The County is striving to keep the public informed about the progress in a speedier manner. Your patience is appreciated, and we apologize for any inconvenience.

 If you have any questions, please contact Richard Kinder, HDR Engineering, Inc. at 208-631-9653 or the Road Department at 208-476-4813.